Aspic Engineering and Construction Co. v. ECC Centcom Constructors LLC

by
The Ninth Circuit affirmed the district court's decision vacating an arbitration award to Aspic, in an action seeking to resolve how much money ECC owed Aspic after ECC terminated for convenience two subcontracts it had awarded to Aspic. The panel held that the arbitrator exceeded his authority and failed to draw the essence of the award from the subcontracts. In this case, the arbitrator did not base his conclusion upon Aspic and ECC's actual past procedures, but upon his rationalization that to enforce the Federal Acquisition Regulation (FAR) clauses on Aspic would be unjust. The panel held that the award disregarded specific provisions of the plain text in an effort to prevent what the arbitrator deemed an unfair result, and therefore such an award was irrational. View "Aspic Engineering and Construction Co. v. ECC Centcom Constructors LLC" on Justia Law