by
Plaintiffs, two groups of cotton farmers, filed suits against the cooperative of which they were members under contract, alleging that they were fraudulently induced to join the cooperative. Plaintiffs’ agreements with the cooperative provided for the arbitration of all disputes under the Federal Arbitration Act (FAA). The cooperative filed a motion to stay the litigation and a motion to compel arbitration. The trial court denied the motions, concluding that the parties’ arbitration agreement was unconscionable. The court of appeals affirmed, reasoning that the agreements were unconscionable because they forced the farmers to “forego substantive rights and remedies afforded by statute.” The Supreme Court reversed, holding that the limitation of statutory remedies was insufficient to defeat arbitration under the FAA. Remanded.View "Venture Cotton Coop. v. Freeman" on Justia Law

by
Plaintiff-general contractor entered into an agreement with Defendant-subcontractor to perform work on a project. A dispute arose between the parties when Plaintiff issued Defendant a notice of termination. The issue was submitted to arbitration, and both parties submitted claims to the arbitrator for money damages. The arbitrator found that Plaintiff’s termination of Defendant was wrongful and granted damages. Plaintiff sought to vacate the arbitrator’s award. The trial court concluded that a release signed by Defendant that waived all claims prior to a certain date barred Defendant’s claims. The Supreme Court vacated the judgment of the superior court, holding that the arbitrator’s decision should have been allowed to stand because it showed due regard for the parties’ release and did not reach an irrational result. View "Berkshire Wilton Partners, LLC v. Bilray Demolition Co." on Justia Law

by
The Gobellans retained Law Firm to defend them and bring suit. Associate was assigned to the case. Associate later left Law Firm and took several clients, including Gobellans, with him. Law Firm sued Associate over client contingency fees, and later settled. Law Firm also sued Gobellans, and moved to compel the dispute to arbitration pursuant to an arbitration clause in the contingency fee agreement between Law Firm and Gobellans. The trial court and court of appeals denied Law Firm’s motion to compel arbitration, concluding that because Law Firm had litigated the fee issue with Associate, it waived its right to arbitrate claims stemming from its fee agreement with Gobellans. The Supreme Court reversed, holding (1) because Law Firm’s litigation conduct involved suing Associate, with whom it had no arbitration agreement, and filing limited pleadings against Gobellans, the conduct did not substantially invoke the litigation process against Gobellans or prejudice them; and (2) thus, Law Firm did not waive its right to arbitrate its dispute with Gobellans. View "Hodges, LLP v. Gobellan" on Justia Law

by
This case arose out of a fee dispute between associated attorneys arising out of mass-tort cases in Copiah County between 2005 and 2010. The first appeal arose out of a joint-venture agreement between Don Mitchell and the law firm of Sweet & Freeese, PLLC. The second appeal stemmed from an alleged oral referral agreement between McHugh Fuller Law Group, PLLC, and the members of the joint venture. The appellants in this consolidated appeal challenged the County Chancery Court’s denial of their motions to compel arbitration of claims brought against them by Mitchell and the McHugh Fuller Law Group, PLLC. Finding no error, the Supreme Court affirmed. View "Freese v. Mitchell" on Justia Law

by
Appellees filed a class-action complaint against a Bank, asserting several claims arising from the Bank’s alleged practice of manipulating customers’ checking-account debit transactions to maximize the amount of overdraft fees charged to each customer. The Bank filed a motion to dismiss, or alternatively, a motion to compel arbitration based on an arbitration provision contained in the Deposit Agreement attached to Appellees’ complaint. In response, Appellees denied the existence of a valid arbitration agreement. The circuit court denied Bank’s motion, ruling that the arbitration provision was unconscionable and, thus, unenforceable. The Supreme Court reversed, holding that because the circuit court did not find that there was a valid arbitration agreement, the case must be remanded to the circuit court to determine whether there was a valid agreement to arbitrate between the parties.View "Bank of the Ozarks, Inc. v. Walker" on Justia Law

by
Southeast Construction, L.L.C. ("SEC") appealed a Circuit Court order enforcing, a previous judgment entered by that court based on an arbitration award in favor of WAR Construction, Inc ("WAR"). Upon review of the facts of this case, the Supreme Court affirmed in part, reversed in part, and remanded for further proceedings. The Court concluded the circuit court erred in finding in a January 9 order that "all liens and claims against SEC ... from WAR's subcontractors/suppliers that filed a lien on the project ... ha[d] been released and/or adequate security ha[d] been provided." Furthermore, the Court concluded the circuit court erred in finding that WAR had "attempt[ed] to comply with what the Supreme Court ordered the circuit court to implement as of May 13, 2011," and that WAR was entitled to have the interest owed under the arbitrators' award and the May 9 judgment calculated from that date. View "Southeast Construction, L.L.C. v. WAR Construction, Inc. " on Justia Law

by
In consolidated cases, thirty-two plaintiffs who signed delayed-deposit check agreements with Zippy Check Advance agreed that Zippy Check could pursue judicial remedies against them to collect the debt, while any and all of their claims would be relegated to arbitration. The circuit courts found the arbitration agreements to be unconscionable and denied Zippy Check’s motions to compel arbitration. The Court of Appeals affirmed as to one version of the agreement and reversed as to the other. Upon review, the Supreme Court found that both versions of the arbitration agreement were so one-sided that they were substantively unconscionable and unenforceable. The Court affirmed in part and reversed in part the judgment of the Court of Appeals and affirmed the judgments of the Circuit Court of Clarke County and the Circuit Court of Newton County. View "Caplin Enterprises, Inc. v. Arrington" on Justia Law

by
The Providers supply outpatient cardiac telemetry (OCT) services, used by doctors to monitor cardiac arrhythmias. The device differs from conventional technology in that it transmits electrocardiographic (EKG) data in real time to certified technicians, who forward the data to a physician. OCT is approved by the FDA, and has long been covered by Medicare and commercial insurers. CIGNA administers employer sponsored health benefit plans. CIGNA pays its in-network providers directly for the services rendered to patients. In 2007, the Providers joined CIGNA’s network by Agreements that set the reimbursement rate and define “Covered Services.” In 2012, CIGNA issued a statement that it would no longer cover OCT “for any indication because it is considered experimental, investigational or unproven.” The 2012 Policy acknowledged that this new position would be trumped by any conflicting language in the coverage policies themselves. In arriving at the new policy, CIGNA relied on the same medical literature it had previously relied upon in concluding that OCT should be covered. The Providers claim that CIGNA indicated that its motive was financial, but refused to reconsider the 2012 Policy. The district court found that the Providers’ claims fell within the arbitration clause of the Agreement. The Third Circuit vacated. The clause at issue is limited in scope to disputes “regarding the performance or interpretation of the Agreement” and the claims at issue do not relate to the performance or interpretation of the Agreement.View "Cardionet Inc v. Cigna Health Corp." on Justia Law

by
The Union filed suit against WUSA-TV, a television station, alleging that the station breached its contractual obligations by laying off a technician. Because the grievance did not "arise under" the 2008 bargaining agreement, and the 2012 agreement was not yet in effect, the district court concluded that the station was not obligated to arbitrate. The court affirmed, concluding that seniority provisions in the 2008 agreement did not create vested or accrued rights and therefore, the grievance was not arbitrable under the 2008 agreement. Nor do the qualified seniority protections against layoffs contained in the 2008 agreement survive expiration under normal principles of contract interpretation. Moreover, the union's extrinsic evidence was itself ambiguous. Finally, the court rejected the Union's claim that the grievance was arbitrable under the 2012 agreement.View "Int'l Brotherhood of Electrical Workers v. Detroit Free Press, Inc." on Justia Law

by
Guardian Builders, LLC, and E. Wayne Tackett appealed a Circuit Court order denying their motion to vacate or modify an arbitration award entered in favor of Randy Uselton and his wife Melissa. In 2010, the Useltons sued Guardian alleging several claims arising from Guardian's construction of a house for the Useltons. Guardian subsequently filed a motion to compel arbitration, and the circuit court granted that motion. In late 2011, the arbitrator entered a final award in favor of the Useltons. Guardian subsequently filed a motion to vacate or modify the arbitration award to the circuit court, to which it attached a copy of the arbitration award. The Useltons filed a 'motion to confirm' the arbitration award. The circuit court entered an order purporting to deny Guardian's motion to vacate or modify the arbitration award, purporting to grant the Useltons' motion to confirm the arbitration award, and purporting to order Guardian to pay $1,421.75 in Better Business Bureau fees and facility costs related to the arbitration. Guardian objected only to a subset of the damages that were awarded the Useltons that were not directly related to the poorly constructed house, specifically, attorney fees and arbitration fees (including both the arbitrator fee and the forum fee charged by the Better Business Bureau of North Alabama ("the BBB"), which administered the arbitration). Furthermore, Guardian argued the arbitrator lacked the authority to award the Useltons attorney fees and arbitration fees. The Supreme Court agreed that the arbitrator exceeded his authority by awarding those remedies. The trial court's judgment was reversed and the case remanded for the trial court to enter a modified judgment subtracting attorney fees and arbitration fees from the award made to the Useltons. View "Guardian Builders, LLC v. Uselton " on Justia Law