Justia Arbitration & Mediation Opinion Summaries
Articles Posted in Real Estate & Property Law
BBC LLC v. LATAH COUNTY DISTRICT COURT
BBC, LLC, contracted Germer Construction, Inc. to provide construction services for a subdivision development. A dispute arose regarding the amount owed, leading to arbitration as required by contract. The arbitrator awarded Germer nearly $1,000,000, including costs and fees. BBC sought a court order to vacate the arbitration award, while Germer requested confirmation of the award and entry of judgment. Germer also moved for a temporary restraining order and preliminary injunction, claiming BBC was dissipating assets. The district court granted an ex parte temporary restraining order restricting BBC’s asset transfers. At a hearing, the district court required BBC to post a $1,000,000 surety bond and Germer a $250,000 bond, characterizing them as “equivalent” to supersedeas bonds, then dissolved the restraining order and denied preliminary injunctive relief.BBC petitioned the Idaho Supreme Court for writs of prohibition or mandamus to vacate the district court’s order and prohibit further pre-judgment asset restrictions, arguing the district court lacked authority to require the bond or injunctive relief solely to secure a potential monetary judgment. The Idaho Supreme Court stayed the district court’s order and sought briefing from Germer and the Attorney General.The Supreme Court of Idaho held that the district court exceeded its authority by requiring BBC to post a surety bond to secure a potential money judgment for an unsecured debt. The court found no rule, statute, or inherent equitable power authorizing such relief in this context. The court issued a writ of review, vacating the district court’s order, including both bond requirements. BBC was found to have no adequate, speedy remedy at law, and the requested writs of prohibition and mandamus were denied. The case was remanded for further proceedings consistent with the opinion. View "BBC LLC v. LATAH COUNTY DISTRICT COURT" on Justia Law
Ivy Fund Manager, LLC v. CDH Real Estate Investment Management Company, Ltd.
A real estate investment firm based in China and another firm based in Singapore entered into a joint venture in 2021 to develop and operate a property near Auburn University. The Chinese firm held an 80% interest, while the Singaporean firm held a 20% interest and managed the venture, with full access to the joint venture’s bank accounts. The Chinese firm alleged that the manager firm made unauthorized transfers from the joint venture’s accounts, ultimately taking over $1 million. Despite partial repayment and assurances, a significant amount remained outstanding.The Chinese firm filed suit in the Lee Circuit Court, Alabama, asserting claims including declaratory judgment, fraudulent misrepresentation, conversion, and fraudulent suppression. The Singaporean firm failed to timely respond to the complaint, leading to requests for default judgment. After some delay, the manager filed an answer and engaged in discovery, but disputes arose over depositions and compliance with court orders. The trial court repeatedly addressed motions for default judgment and issues of discovery noncompliance, particularly regarding the failure of the manager’s CEO to appear for deposition. The manager later moved to compel arbitration, citing joint venture agreements containing arbitration clauses; however, the trial court ultimately entered a default judgment on liability for the Chinese firm, reserving damages, and deemed the motion to compel arbitration moot.On appeal, the Supreme Court of Alabama considered whether it had jurisdiction, given that the lower court’s judgment did not resolve damages. The Supreme Court of Alabama held that the order was interlocutory and not appealable because it did not determine damages. The court concluded that the default judgment’s interlocutory nature was not altered by the ruling on the arbitration motion, and accordingly, dismissed the appeal for lack of a final judgment. View "Ivy Fund Manager, LLC v. CDH Real Estate Investment Management Company, Ltd." on Justia Law
MAPP v. Floor and Decor
A national flooring retailer contracted with a Louisiana-based construction management company for the construction of a retail store in Metairie, Louisiana. The relationship soured after the retailer terminated the agreement, allegedly due to delays. Shortly after termination, the construction company disputed that it had breached the contract and demanded payment for work performed. The retailer did not respond to the payment demand.The construction company filed suit in the United States District Court for the Middle District of Louisiana under the Louisiana Private Works Act, seeking recovery for the work performed. The retailer moved to compel arbitration based on the agreement’s dispute resolution provision and also sought to transfer the case. The district court granted the transfer to the United States District Court for the Eastern District of Louisiana and denied the motion to compel arbitration without prejudice. When the motion to compel arbitration was renewed in the new court, the district court denied it again, concluding the retailer had not followed the prerequisite steps outlined in the contract’s dispute resolution process.On appeal, the United States Court of Appeals for the Fifth Circuit conducted de novo review. The appellate court determined that the arbitration clause in the contract, which gave the retailer sole discretion to elect arbitration, was a contract of adhesion under Louisiana law. Applying state contract principles and relevant Louisiana Supreme Court precedent, the court found that the lack of mutuality and the imbalance in bargaining power rendered the clause unenforceable. The court held that the arbitration provision was adhesionary and thus invalid, and affirmed the district court’s denial of the motion to compel arbitration. View "MAPP v. Floor and Decor" on Justia Law
Neils Point, LLC v. Grady
Neils Point, LLC owns a farm property in Harpswell, Maine, which it leased to Joseph and Laura Grady for agricultural use. The Gradys resided on the property and operated the farm under successive lease agreements, culminating in a 2017 extension titled “Commercial Agricultural Lease Agreement.” This lease specified that it was not a residential rental, set rent as a percentage of the farm’s net proceeds, and required arbitration for disputes. Neils Point alleged that the Gradys breached the lease by miscalculating rent, failing to pay on time, and not using the land as productive cropland.After Neils Point initiated arbitration in 2024, the Gradys responded by admitting the dispute was subject to arbitration and made their own arbitration demand under the lease. The arbitration hearing was held in July 2025, with both parties participating fully and without objection to either the process or the arbitrability of the dispute. The arbitrator found in favor of Neils Point, concluding that the Gradys breached the lease by improperly deducting expenses, failing to pay rent, and not maintaining the farm’s productivity. Damages were awarded, and the Gradys were ordered to vacate the property.The Cumberland County Superior Court confirmed the arbitration award and denied the Gradys’ subsequent motion to vacate, in which they argued for the first time that the arbitration provision was void because the lease was residential and the arbitrator exceeded his authority. The Maine Supreme Judicial Court affirmed the judgment, holding that the Gradys’ participation in arbitration without objection waived their right to challenge the validity of the arbitration clause or the arbitrator’s authority. The Court further held that the arbitrator’s construction of the lease was rational, and thus confirmation of the award was proper. View "Neils Point, LLC v. Grady" on Justia Law
Cross v. Albright
Two neighboring landowners, who are related by marriage, became involved in multiple property disputes, including disagreements over joint ownership and access to ditches and land. To resolve these disputes, one party filed two complaints in the District Court of Fremont County: one seeking an easement for ditch access and another seeking partition of jointly owned land. The parties also had related petitions pending before the Board of Control. During litigation, they participated in mediation and signed an email outlining terms of a purported global settlement agreement, which included provisions for access to ditches, maintenance rights, restrictions on visible storage, and the drafting of a formal settlement by one party’s attorney.After mediation, as the parties attempted to formalize the agreement, new disagreements arose regarding how to implement the access and storage restriction provisions. Each party filed a motion to enforce their interpretation of the settlement; one sought a recordable easement and restrictive covenant, while the other argued those terms exceeded the agreement. The District Court of Fremont County held a hearing to consider the motions, reviewed the parties’ filings and affidavits, and ultimately found that the agreement lacked essential terms, particularly regarding implementation of ditch access and the visual storage restriction. The court determined there was no meeting of the minds and denied both motions to enforce, as well as a request for sanctions.The Supreme Court of Wyoming reviewed the appeal. It held that the district court did not violate due process, as the issue of contract formation was properly considered and the parties had notice and opportunity to argue their positions. The Supreme Court agreed with the district court’s finding that no enforceable settlement agreement existed due to lack of mutual assent on material terms. It further held that Cross was not entitled to attorney’s fees, as there was no enforceable contract providing for such fees. The Supreme Court affirmed the district court’s order. View "Cross v. Albright" on Justia Law
J.C. Cannistraro, LLC v. Columbia Construction Co.
A general contractor and a subcontractor entered into agreements for the construction and renovation of a facility. The subcontracts required disputes to be resolved by arbitration pursuant to the rules of the American Arbitration Association. The subcontractor performed work and submitted invoices, but the general contractor, while timely rejecting the invoices and providing reasons, failed to include the good faith certification required by the Massachusetts prompt pay act. The contractor later paid the invoices after an arbitrator determined that the invoices were deemed approved due to the lack of timely certification. Subsequently, the contractor filed a counterclaim in arbitration seeking recoupment of those payments, arguing the invoices were not fair and reasonable.The subcontractor initially brought suit in the Massachusetts Superior Court, which was then compelled to arbitration per the contract. During arbitration, the arbitrator found that the contractor’s failure to timely certify its rejection of the invoices resulted in the invoices being deemed approved and ordered payment to the subcontractor. After payment, the arbitrator allowed the contractor’s counterclaim for recoupment. Following evidentiary proceedings, the arbitrator ruled in favor of the contractor, awarding partial recoupment. The subcontractor moved in the Superior Court to vacate this award, arguing that the arbitrator exceeded his authority. Relying on J.C. Cannistraro, LLC v. Columbia Construction Co., the Superior Court judge vacated the recoupment portion of the arbitration award, finding that the contractor had asserted defenses before paying the invoices, contrary to precedent.The Supreme Judicial Court of Massachusetts reviewed the matter on direct appellate review. It held that the arbitrator did not exceed his authority because the award was not prohibited by law nor did it violate public policy. The court determined that the prompt pay act did not expressly prohibit recoupment in these circumstances and that the arbitrator’s actions were within the broad scope granted by the parties’ agreement and the arbitration rules. The judgment vacating the arbitration award was reversed and the matter remanded for confirmation of the arbitration award. View "J.C. Cannistraro, LLC v. Columbia Construction Co." on Justia Law
Khalsa v. Ridnour
Two neighbors in Bonner County, Idaho, own adjacent properties—one is lakefront and the other sits directly behind it without lake access. After years of disputes over easements relating to beach, lake, and parking access, the parties entered litigation. During trial, the district court mediated a settlement, which was read into the record and later formalized as a Stipulated Agreement and Order. This agreement outlined the parties’ rights to use the properties and set procedures for mediation and arbitration if further disputes arose.After signing the agreement and a minor modification by the district court, further conflicts emerged, especially regarding the construction and location of one party’s patio, use of a parking easement, a maintenance corridor, and a sprinkler system. Pursuant to the agreement, the unresolved issues were submitted to arbitration. The arbitrator ruled in favor of the lakefront property owner on all issues, finding that the other party had not complied with the agreement. The dissatisfied party then moved in the District Court of the First Judicial District to vacate the arbitration award, alleging bias and that the arbitrator had exceeded his authority. The district court denied the motion, finding the arbitrator had acted within the scope of his authority.On appeal, the Supreme Court of the State of Idaho reviewed the district court’s denial. The Court held that the arbitrator’s decisions were within the authority granted by the parties’ agreement and the Idaho Uniform Arbitration Act. The Court found no evidence of bias and concluded the arbitrator had not rewritten or exceeded the terms of the agreement, but rather interpreted and applied it as authorized. Therefore, the Supreme Court affirmed the district court’s denial of the motion to vacate the arbitration award and granted attorney fees on appeal to the prevailing party under Idaho Code section 12-121. View "Khalsa v. Ridnour" on Justia Law
Eastern Steel v. Int Fidelity Ins. Co.
A steel subcontractor was hired to perform work for a university construction project and entered into a subcontract with the general contractor. The general contractor began defaulting on payments, prompting the subcontractor to notify the surety insurance company, which had issued a payment bond guaranteeing payment for labor, materials, and equipment. The surety made partial payment but disputed the remaining amount. The subcontractor then demanded arbitration against the contractor, with the surety notified and invited to participate. The contractor filed for bankruptcy and did not defend in arbitration, nor did the surety participate. The arbitrator awarded the subcontractor damages, including attorneys’ fees and interest, and the award was confirmed in court. The subcontractor sought to enforce the arbitration award against the surety, including attorneys’ fees and prejudgment interest, and also brought a bad faith claim under Pennsylvania’s insurance statute.The Centre County Court of Common Pleas initially excluded evidence of the arbitration award against the surety at trial and ruled the surety was not liable for attorneys’ fees or bad faith damages. A jury found for the subcontractor on the underlying debt, and the court awarded prejudgment interest at the statutory rate. Both parties appealed. The Superior Court held the arbitration award was binding and conclusive against the surety, who had notice and opportunity to participate, and affirmed liability for attorneys’ fees related to pursuing the contractor in arbitration. The court rejected the bad faith claim, holding the statute did not apply to surety bonds, and confirmed the statutory interest rate.On appeal, the Supreme Court of Pennsylvania affirmed in all respects. It held that Pennsylvania’s insurance bad faith statute does not apply to surety bonds, based on statutory language. The court also held that the surety is bound by the arbitration award against its principal, and is liable for attorneys’ fees incurred in arbitration and prejudgment interest at the statutory rate. View "Eastern Steel v. Int Fidelity Ins. Co." on Justia Law
Khalsa v. Ridnour
The dispute centers on two neighboring property owners at Priest Lake, Idaho, whose properties are subject to several easements, and who have a history of disagreements concerning the use of a shared beach, lake access, and parking. The parties previously reached a court-mediated settlement agreement addressing these issues, which included a provision for future mediation and arbitration of disputes. Disagreements soon arose, particularly over the construction of a patio by one owner, leading the parties to arbitration as provided by their agreement. The arbitrator, after considering substantial evidence and briefing, ruled in favor of one party on all contested issues, including the patio’s location and construction, the use of easements, and parking arrangements.Prior to this appeal, the District Court of the First Judicial District, Bonner County, reviewed a motion to vacate the arbitration award. The moving party argued that the arbitrator exceeded his authority and was biased, primarily because the award was unfavorable and allegedly altered the terms of the court-approved settlement agreement. After considering the arguments, the district court denied the motion, finding that the arbitrator had acted within the scope of his authority and that no evidence of bias was presented.Upon review, the Supreme Court of the State of Idaho affirmed the district court’s decision. The court held that under Idaho’s Uniform Arbitration Act, judicial review of arbitration awards is extremely limited and does not allow for overturning an award simply due to alleged errors in law or fact, or because the outcome was unfavorable. The court found no evidence that the arbitrator exceeded his authority or acted with bias. Additionally, the court awarded attorney fees on appeal to the prevailing party under Idaho Code section 12-121, concluding the appeal was frivolous and without foundation. The district court’s denial of the motion to vacate was affirmed. View "Khalsa v. Ridnour" on Justia Law
Peterson v. Zhang
Two neighbors in a residential community disagreed about a tree branch that obstructed one neighbor’s view. Jinshu Zhang, the owner seeking the view, used his homeowners association’s dispute resolution process, which included mediation and arbitration services provided by Charles Peterson, an independent mediator. When the association dismissed Zhang’s application, Zhang sued Peterson for breach of fiduciary duty, claiming Peterson was a director or officer of the association and thus owed him such a duty. However, Peterson was neither a director nor an officer, but an independent contractor. Zhang lost his lawsuit against Peterson following a nonsuit at trial, and did not appeal.After that case concluded, Peterson filed a malicious prosecution action against Zhang, alleging Zhang’s earlier suit was baseless and continued without probable cause once Zhang had evidence Peterson was not an officer or director. In response, Zhang filed a special motion to strike under California’s anti-SLAPP statute (Code of Civil Procedure section 425.16), seeking to dismiss Peterson’s malicious prosecution claim. The Superior Court of Los Angeles County denied Zhang’s anti-SLAPP motion, finding Peterson’s case had at least minimal merit based on evidence showing Zhang lacked probable cause and may have acted with malice in pursuing the prior suit.The California Court of Appeal, Second Appellate District, Division Eight, reviewed Zhang’s appeal. The court affirmed the denial of Zhang’s anti-SLAPP motion, holding that the denial of a discretionary sanctions motion in the underlying suit did not establish probable cause under the “interim adverse judgment rule,” and did not bar the malicious prosecution claim. The court concluded that Peterson’s evidence on lack of probable cause and malice was sufficient to allow his case to proceed, and remanded for further proceedings. View "Peterson v. Zhang" on Justia Law